Project name Client Scope of work Year
S/S 110/20 kV Crikvenica, Croatia, 110kV switchyard reconstruction HOPS d.o.o. Design for Construction 2014.
S/S 110/35/20 kV Poreč, Croatia, 110kV switchyard reconstruction HOPS d.o.o. Design for Construction 2014.
S/S 110/10(20) kV Medulin, Croatia, control building and plateau construction, civil part HEP d.d. Design for Construction 2014.
Steel Mill ABS Sisak, Croatia, new reacror 33 kV, 1200 A instalation ABS Sisak Main Design 2014.
S/S 110/35/20 kV Nedeljanec, Croatia, switchyard reconstruction and extension HEP d.d. Main Design 2014.
S/S 110/35 kV Pračno, Croatia, 110 kV switchyard reconstruction HEP d.d. Site Supervision 2014.
S/S 110/20/10 kV Kneginec, Croatia, new 110 switchyard HEP d.d. Site Supervision 2014.
HPP Komani, Albania, unit 1-4 main transformer oil containment Andritz Hydro Main Design, Design for Construction 2014.
S/S 110/10 kV Plamen Požega, Croatia, new 110 and 10 kV switchyard Plamen d.o.o. Site Supervision 2013.
ARNA Algeria, neutral point 220 kV steel structure Končar Power Transformers Ltd. Main Design, Design for Construction 2013.
Thermal power station Sviloza, Bulgaria, three-phase non-segregated bus duct aluminium structure Končar Power Transformers Ltd. Main Design, Design for Construction 2013.
Zouk PP, Libanon, step-up transformers (UBF) steel structure Končar DIST d.d. Main Design, Design for Construction 2013.
S/S 110/35/10 kV Đakovo 2, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2013.
S/S 110/35/10 kV Đakovo 2, Croatia, transformer foundations reconstruction HEP d.d. Main Design, Design for Construction 2013.
S/S 110/35/10 kV Slatina, Croatia, 110 kV transformer foundations reconstruction HEP d.d. Main Design, Design for Construction 2013.
S/S 110/20 kV Tupljak, Croatia, new 110 kV switchyard HEP d.d. Design for Construction 2013.
S/S 400/110 kV Ernestinovo, Croatia, new 150 Mvar reactor instalation and 110 kV reactor bay extension HEP d.d. Main Design 2013.
S/S 110/35 kV Požega, Croatia, 110 kV switchyard extension Plamen d.o.o. Design for Construction 2013.
S/S 110/10 kV Plamen Požega, Croatia, new 110 and 10 kV Switchyard Plamen d.o.o. Design for Construction 2013.
S/S 110/20(10) kV Pag, Croatia, 110 kV switchyard extension HEP d.d. Design for Construction 2013.
Power Plant EL TO Zagreb, Croatia, 110 kV and 20 kV switchyard reconstruction and extension HEP d.d. Main Design 2012.
S/S 110/35 kV Požega, Croatia, 110 kV switchyard extension Plamen d.o.o. Main Design 2012.
S/S 110/10 kV Plamen Požega, Croatia, new 110 and 10 kV Switchyard Plamen d.o.o. Main Design 2012.
S/S 110/35 kV Kaštela, Croatia, 110 kV and 35 kV switchyard extension HEP d.d. Main Design, Design for Construction 2012.
S/S 400/110 kV Ilisu, Turkey, new 400 kV and 110 kV switchyard Andritz Hydro Main Design, Design for Construction 2012.
National Dispatch Center (HEP) Zagreb, Croatia, reconstruction HEP d.d. Site Supervision 2012.
S/S 110/35/10 kV Belišće, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2012.
S/S 110/30/10 kV Našice, Croatia, switchyard reconstruction and new 20 kV switchyard HEP d.d. Design for Construction 2012.
S/S 110/35/10 kV Slatina, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2012.
S/S 220/110/35 kV Pehlin, Croatia, 220 kV switchyard reconstruction and new 110 kV GIS switchyard HEP d.d. Design for Construction 2011.
Pometeno brdo Wind Farm, Croatia Končar Obnovljivi Izvori d.o.o. Site Supervision 2011.
S/S 35/0.575/0.4 kV DIV Knin, Croatia, new substation DIV Knin d.d. Main Design, Design for Construction 2011.
S/S 35/10(20) kV Bjelovar, Croatia, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2011.
Pometeno brdo Wind Farm, Croatia Končar KET d.d. Main Design, Design for Construction 2011.
S/S 380/220/110/10 kV Konjsko, Croatia, 110 kV switchyard extension and new 20 kV switchyard Končar KET d.d. Main Design, Design for Construction 2011.
HPP Rama, Bosnia and Herzegovina, 220 kV transformer cells reconstruction Končar Power Transformers Ltd. Main Design, Design for Construction 2011.
S/S 500/400/220 kV Zestafoni, Georgia, new substation Siemens Main Design 2011.
S/S 500/400/220 kV Akhaltsikhe, Georgia, new substation Siemens Main Design 2011.
S/S 220/110/35 kV Vau Dejes, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2011.
S/S 220/110/35 kV Komani, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2011.
S/S 220/110/35 kV Fierza, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2011.
S/S 110/35 kV Palaj, Kosovo, reconstruction and extension ABB d.o.o. Main Design, Design for Construction 2011.
S/S 110/35/10 kV Nova Gradiška, Croatia, 110 kV switchyard reconstruction HEP d.d. Site Supervision 2011.
S/S 110/30/10 kV Jarun, Croatia, 110 kV switchyard reconstruction HEP d.d. Site Supervision 2011.
Tunnel Učka, Croatia, 10(20)/0,4 kV S/S1-S/S8 reconstruction BINA ISTRA d.o.o. Main Design, Design for Construction 2010.
S/S 110/30/10 kV Županja, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2010.
S/S 400/220/110 kV Melina, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2010.
S/S 110/10(20) kV Kutina, Croatia, 110/10(20) kV switchyard reconstruction and extension and new control building HEP d.d. Main Design, Design for Construction 2010.
S/S 220/110/10 kV Prizreni 2, Kosovo, reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2010.
S/S 220/110/35 kV Pehlin, Croatia, 220 kV switchyard reconstruction and new 110 kV GIS switchyard HEP d.d. Main Design 2010.
S/S 110/30/10 kV Rijeka, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2010.
S/S 110/30/10 kV Nova Gradiška, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2010.
S/S 110/30/10 kV Jarun, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2010.
Escalao de Jusante, Portugal, new 60 kVsubstation Andritz Hydro Main Design, Design for Construction 2010.
Smith Transformatoren, Nijmegen, Netherlands, steel structure for oil storage tanks Končar KET d.d. Main Design, Design for Construction 2010.
S/S Chacayes, Chile, new 230 kV substation Andritz Hydro Main Design, Design for Construction 2010.
Fushe Kruja Cement Factory SH.P.K., Elbasan, Albania, S/S 220/6 kV switchyard extension ABB Hrvatska Main Design, Design for Construction 2010.
Zagreb -Sisak highway, Croatia, section Velika Gorica – Lekenik HAC d.d. Site Supervision 2009.
Zagreb – Sisak highway, Croatia, section Jakuševac -Velika Gorica HAC d.d. Site Supervision 2009.
S/S 220/110 kV Kosova A, Kosovo, 110 kV line connection HELB d.o.o. Main Design, Design for Construction 2009.
S/S 2, Zagreb Airport, Croatia, 20 kV substation reconstruction Zračna luka Zagreb d.d. Main Design, Design for Construction 2009.
Zagreb Airport, Croatia, 20 kV cable canalization Zračna luka Zagreb d.d. Main Design, Design for Construction 2009.
Escalao de Montante, Portugal, new 220 kV switchyard Andritz Hydro Main Design, Design for Construction 2009.
S/S Methana, Greece, 20 kV switchyard extension EFACEC Contracting Central Europe
GmbH
Main Design, Design for Construction 2009.
S/S 110/35/10 kV Valpovo, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2009.
S/S 35/10(20) kV Seline, Croatia, new substation HEP d.d. Main Design 2009.
Ambuklao and Binga, Philippines, new 220 kV switchyard Andritz Hydro Main Design, Design for Construction 2009.
S/S Sapugaskanda, Ceylon, new 132 kV switchyard VA TECH T&D GmbH Main Design, Design for Construction 2009.
S/S Katunayake, Ceylon, new 132 kV switchyard VA TECH T&D GmbH Main Design, Design for Construction 2009.
S/S Bolawatta, Ceylon, new 33 kV switchyard VA TECH T&D GmbH Main Design, Design for Construction 2009.
S/S 110/20 kV Tupljak, Croatia, new 110 kV switchyard HEP d.d. Main Design 2009.
S/S 220/110/35 kV Elbasan 1, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2009.
S/S 220/110/35 kV Tirana 1, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2009.
S/S 220/110/35 kV Fier, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2009.
S/S 110/00 kV Samobor, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design, Design for Construction 2009.
S/S 10/0,4 kV TS 5 i TS 6, Port of Ploče, Croatia, new substations Lučka upravaPloče d.d. Main Design, Design for Construction 2008.
S/S 137/10(20)/0,4 kV Sesvetski Kraljevec, Croatia, new substation Končar KET d.d. Main Design, Design for Construction 2008.
S/S 110/35 kV Kaštela, Croatia, 110 kV switchyard reconstruction Končar KET d.d. Main Design, Design for Construction 2008.
S/S 110/35/10(20) kV Mostar 9, Bosnia and Herzegovina, new substation Dalekovod d.d. Main Design, Design for Construction 2008.
Aproveitamento hidroeléctrico do Douro Internacinal, Bemposta, Portugal, 400 kV gantry and apparatus supports Andritz Hydro Main Design, Design for Construction 2008.
Power Plant Plomin, Croatia, 110 switchyard extension HEP d.d. Main Design, Design for Construction 2008.
S/S 110/20 kV Buzet, Croatia, auxiliary transformers positioning HEP d.d. Main Design, Design for Construction 2008.
S/S 220/110 kV Đakovo, Croatia, 220 kV bus couplar bay reconstruction Končar KET d.d. Main Design, Design for Construction 2007.
Power Plant Plomin, Croatia, 220 transformer bay reconstruction HEP d.d. Main Design, Design for Construction 2007.
S/S 110/20 kV Bushat, Albania, new substation Končar KET d.d. Main Design, Design for Construction 2007.
S/S 110/20 kV Koplik, Albania, new substation Končar KET d.d. Main Design, Design for Construction 2007.
S/S 400/110 kV Bitola, Macedonia, switchyard reconstruction and extension Dalekovod d.d. Main Design, Design for Construction 2007.
S/S 220/110/35 kV Vau Dejes, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2006.
S/S 110/35/20 kV Skhodra 2, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2006.
S/S 110/35/20 kV Skhodra 1, Albania, switchyard reconstruction and extension Končar KET d.d. Main Design, Design for Construction 2006.
S/S 110/35 kV Pračno, Croatia, 110 kV switchyard reconstruction HEP d.d. Main Design 2006.